African Oilfield in Focus: The Gabon’s Dussafu Marin Permit


Published: Tuesday June 4, 2024
By: Oilfield Africa Review

Gabon is sub-Saharan Africa’s fourth largest producer and exporter of crude oil. The Dussafu Marin Permit is a Development and Exploitation license with multiple discoveries and prospects lying within a proven oil and gas play fairway within the Southern Gabon Basin. To the north west of the block is the Etame-Ebouri Trend, a collection of fields producing from the pre-salt Gamba and Dentale sandstones, and to the north are the Lucina and M’Bya fields which produce from the syn-rift Lucina sandstones beneath the Gamba.

Dussafu is operated by BW Energy Gabon and Panoro’s  interest in the license is 17.5%. There are multiple oil fields within the Dussafu Permit: Moubenga, Walt Whitman, Ruche, Ruche North East, Tortue, Hibiscus and Hibiscus North. The latter five fields were discovered by Panoro and JV partners. During 2021 gross production from Dussafu Marin amounted to 4.1 MMbbls. The gross 2P reserves on the license were estimated as of end 2021 to be approximately 99.7 million barrels and gross 2C resources 38.7 MMbbls.

The first field in the Dussafu EEA area, Tortue, started oil production in September 2018 from two initial horizontal development wells drilled in the first half of 2018. In 2019/2020 a further two development wells were drilled and brought onstream with the final two wells being drilled and brought onstream in 2021, making a total of six production wells on the field. The oil from the Tortue wells is produced via subsea trees and flowlines to a leased FPSO for processing, storage and export.

The next phase of development at Dussafu is the Hibiscus and Ruche fields, which are being developed together and tied back to the BW Adolo FPSO stationed at Tortue. Final Investment Decision was taken for the project in 2019, and the development consists of six wells in Hibiscus and Ruche in phase 1, which will be followed by another six or seven wells, including wells in the Ruche NE field, in phase 2. 

The BW MaBoMo production facility, flexible pipelines and risers connecting the new facility to the BW Adolo FPSO were installed in 2022. Phase 1 production drilling commenced in early January 2023 and the first well was put into production in April 2023 as planned. Once all six wells at the Hibiscus Ruche phase 1 development have been completed production at Dussafu is expected to reach levels of around 40,000 barrels of oil per day on a gross basis.

The exploration potential in Dussafu is significant with several Gamba and Dentale prospects in addition to the already discovered resources, and in future years additional prospects may be targeted.

Sponsored Partners

Discover our premium partners and explore their innovative solutions in the industry
Technology
BW Elara FDU to Produce 40 mml/d Fresh Water from Salt Water
Friday November 14, 2025
Nigeria
Nigeria Boasts of First Methanol Production Facility Plant
Thursday November 13, 2025

Sponsored Partners

Discover our premium partners and explore their innovative solutions in the industry

SUBSEA
DeepOcean Wins Subsea Installation Work on Equinor Gas Project
Thursday November 13, 2025
Côte d'Ivoire
Côte d’Ivoire to Drill More Wells, as Baobab FPSO Goes on Dry Dock
Wednesday November 12, 2025
Hydrogen
OMV, Masdar to Build New Green Hydrogen Plant in Austria
Monday November 10, 2025
Conferences & Exhibitions
Nigeria’s Olu Verheijen Joins G20 Africa Energy Investment Forum Amid Strategic Reforms
Sunday November 9, 2025
Conferences & Exhibitions
ADIPEC 2025: NNPC Ltd Calls for Pragmatic Partnerships, Investment to End Energy Poverty
Saturday November 8, 2025
Conferences & Exhibitions
ADIPEC 2025: Energy, Finance, Technology Leaders Call for Accelerated Investment
Friday November 7, 2025
Conferences & Exhibitions
ADIPEC 2025: Technology Leaders call for Bold, Coordinated Investment in AI
Friday November 7, 2025
Conferences & Exhibitions
Mozambique Cyber Revolution Summit 2026: Harnessing Innovation for a Safer Cyber Future
Friday November 7, 2025