Maritania

Allseas completes infield pipelay scope for GTA FLNG offshore Mauritania and Senegal


Published: Wednesday February 21, 2024
By: Oilfield Africa Review

Allseas Pioneering Spirit offshore vessel has completed the infield pipelay scope for BP’s ultra-deepwater GTA liquified natural gas project offshore Mauritania and Senegal. Two months after arriving in the field, production crew welded, scanned and field joint coated the final piece of pipe for the second 16-inch export gas line.

This on time project completion milestone was achieved few days after the announcement of the arrival of The floating liquefied natural gas (FLNG) vessel that is a core component of the Greater Tortue Ahmeyim (GTA) LNG project at its destination on the Mauritania and Senegal maritime border. The FLNG vessel, Gimi, is at the heart of the GTA Phase 1 development, operated by bp with partners, Kosmos Energy, PETROSEN and SMH.

Safely landed in a 2-metre target box at 2400 metre water depth, the pipeline will be recovered in J-mode configuration to install the termination assembly. To make this happen, the vessel aft has been fitted with a bespoke J-mode frame with a 1000-tonne load capacity. Designed, built and installed on board in only eight weeks by our engineering and fabrication teams, it typifies Allseas “can do” mentality.

The pipelay scope comprises approx. 75 km of 16-inch export lines and 10 km of 10-inch CRA infield lines, some of the pipeline infrastructure exceeding 2700 metres water depth at the deep end! To meet our own ambitious production rate, the main firing line and double jointing facilities on Pioneering Spirit have run in parallel throughout the campaign. Pioneering Spirit will conclude the offshore works by installing the six outstanding flowline termination assemblies.

“Our Agile approach was a key to quick and efficient start to the project and decision-making process throughout the offshore campaign. Thanks to great collaboration between the onshore and offshore teams, we’ve overcome all challenges faced during the project preparation and execution phases and met all milestones without delay.” Allseas Project Manager, Laurent Beghin said.

BP was in October 2023 awarded Allseas with a contract to perform the subsea pipelay scope for the GTA natural gas project. GTA Phase 1 is set to produce around 2.3 million tonnes of LNG per year. The innovative project is expected to produce LNG for more than 20 years, enabling Mauritania and Senegal to become a global LNG hub

Sponsored Partners

Discover our premium partners and explore their innovative solutions in the industry

Carbon Capture
Nigeria, APRI Collaborates on Methane Mitigation and Reduction
Tuesday August 19, 2025
South Africa
South Africa launches first-ever Renewable Energy Offtake Programme
Tuesday August 19, 2025
Conferences & Exhibitions
Century Group Joins African Energy Week 2025 as Gold Partner
Tuesday August 19, 2025
Solar energy
CrossBoundary Energy to Deploy US$40M Clean Energy Investment in Africa
Tuesday August 19, 2025
Acquisition And Merger
ConocoPhillips Divests Marathon Oil’s Anadarko Basin Assets for $1.3 Billion
Tuesday August 19, 2025
Côte d'Ivoire
EXIM Bank Approves $47 Million Technology Deal to Côte d’Ivoire
Tuesday August 19, 2025
Gas & Power
Nigeria Commissions WAGL’s 40,000 CBM LPG Vessel in South Korea
Tuesday August 19, 2025