Gabon

BW Energy Progresses In Gabon Operations, Dussafu And Tortue Fields


Published: Thursday January 27, 2022
By: Oilfield Africa Review

BW Energy today provides an update on the operations and development of the Dussafu Marin license in Gabon. The Company will publish financial figures for the fourth quarter and the annual report for 2021.

Gross production from the Tortue field averaged approximately 12,250 barrels of oil per day in the fourth quarter of 2021, amounting to a total gross production of approximately 1.1 million barrels of oil for the period. The increase in production compared to the third quarter of 2021 was mainly due to the start of production from the two new Tortue phase-2 wells. The previously communicated shortage of gas lifting capacity continued to impact operations during the quarter, with stable production from four of the six Tortue wells.

BW Energy completed two liftings in the quarter and realised an average price of USD 79 per barrel. Production cost (excluding royalties) was approximately USD 27 per barrel. The overall production cost includes approximately USD 1.0 million of costs related to the continued handling of the COVID-19 pandemic in the period.

BW Energy’s share of gross production was approximately 830,000 barrels of oil. The net sold volume, which is the basis for revenue recognition in the financial statement, was 1,170,000 barrels including 130,000 barrels of quarterly Domestic Market Obligation (DMO) deliveries with an over-lift position of  107,000 barrels at the end of the period.

BW Energy had a cash balance of USD 150 million at 31 December 2021, compared to USD 170 million at 30 September 2021. The decrease was mainly due to investments related to the Hibiscus/Ruche project activities. The payment for the second lifting, which was completed in late December, was not received by year-end.

In late January, BW Adolo commenced a 12-day planned annual maintenance shutdown, which will impact production in the first quarter of 2022. As part of this shutdown, the company is exploring interim measures to improve gas lift capacity until the installation of a permanent compressor, which is expected in the fourth quarter 2022.

Sponsored Partners

Discover our premium partners and explore their innovative solutions in the industry

African
TotalEnergies Grabs Four Exploration Permits Offshore Liberia 
Wednesday September 17, 2025
Conferences & Exhibitions
Oilserv Chairman/GCEO Takes Company’s Innovative Expertise to Africa Oil Week (AOW)   
Wednesday September 17, 2025
People
Petralon Energy Appoints Pius Adegoke as Asset Manager
Wednesday September 17, 2025
Global
Eco (Atlantic) Secures Assets Extension, a Farmout in Namibia
Wednesday September 17, 2025
African
NUPRC Oversees Conversion Of First PPL From 2020 Bid Round
Saturday September 13, 2025
Rig Count
Nigerian Upstream Regulator Revokes Drilling Licence Of Oritsemeyin Rig
Saturday September 13, 2025
People
Celebrating 20 Under 40 Women in Energy Rising Stars 2025
Saturday September 13, 2025