Senegal

FLNG Gimi Received First Gas from the GTA Field


Published: Saturday January 25, 2025
By: Oilfield Africa Review

Golar LNG Limited has announced that on January 18, 2025, FLNG Gimi received feed gas from the bp operated FPSO on the Greater Tortue Ahmeyim (GTA) project offshore Mauritania and Senegal. Full commissioning of the FLNG has now commenced.

Prior to achieving this key milestone, gas from the LNG carrier British Sponsor was being used to undertake advanced commissioning work. Receipt of gas from the FPSO allows the full commissioning activity to ramp up. The first LNG export cargo is now expected within Q1 2025, and full Commercial Operations Date (“COD”) is expected within Q2 2025, subject to all conditions being met.

First gas to the FLNG will result in the final upward adjustment to the Commissioning Rate under the commercial reset agreed in August 2024. COD will trigger the start of the 20-year Lease and Operate Agreement that unlocks the equivalent of around $3 billion of Adjusted EBITDA Backlog (Golar’s share) and recognition of contractual payments comprised of capital and operating elements in both the balance sheet and income statement.

Sponsored Partners

Discover our premium partners and explore their innovative solutions in the industry

Offshore Vessels
SBM Offshore’s FPSO One Guyana produces First Oil
Monday August 11, 2025
Conferences & Exhibitions
Ammat Global Resources Targets 70% Production Growth in Congo
Monday August 11, 2025
Solar energy
Scatec Secures Long-term 142 MW Solar PV Plant Project Financing
Wednesday August 6, 2025
African
Akrake Petroleum, Block 1 Sèmè Field, Benin S.A.
Wednesday August 6, 2025
Carbon Capture
Halliburton Secures NET’s Carbon Capture and Storage Contract
Wednesday August 6, 2025