Senegal

FLNG Gimi Received First Gas from the GTA Field


Published: Saturday January 25, 2025
By: Oilfield Africa Review

Golar LNG Limited has announced that on January 18, 2025, FLNG Gimi received feed gas from the bp operated FPSO on the Greater Tortue Ahmeyim (GTA) project offshore Mauritania and Senegal. Full commissioning of the FLNG has now commenced.

Prior to achieving this key milestone, gas from the LNG carrier British Sponsor was being used to undertake advanced commissioning work. Receipt of gas from the FPSO allows the full commissioning activity to ramp up. The first LNG export cargo is now expected within Q1 2025, and full Commercial Operations Date (“COD”) is expected within Q2 2025, subject to all conditions being met.

First gas to the FLNG will result in the final upward adjustment to the Commissioning Rate under the commercial reset agreed in August 2024. COD will trigger the start of the 20-year Lease and Operate Agreement that unlocks the equivalent of around $3 billion of Adjusted EBITDA Backlog (Golar’s share) and recognition of contractual payments comprised of capital and operating elements in both the balance sheet and income statement.

Sponsored Partners

Discover our premium partners and explore their innovative solutions in the industry
Conferences & Exhibitions
Global Energy Investors Assemble at Gas Investment Forum 2026, as Event Kicks Off
Tuesday September 29, 2026
Nigeria
NIPCO Group Plans $3bn Floating LNG Project Facility in Nigeria
Saturday September 26, 2026

Sponsored Partners

Discover our premium partners and explore their innovative solutions in the industry

Conferences & Exhibitions
ADIPEC 2026 to Mobilize Investment in Resilient, Intelligent Energy Systems that Power Global Growth
Friday September 25, 2026
Nigeria
NCDMB Deepens Energy Ties with China, Seeks Boost in Manufacturing
Wednesday September 23, 2026
Block Licences
Pertamina Expresses Interest in Nigeria’s Oil Blocks, Opens Talks with NUPRC
Monday September 21, 2026