Cameroon

Tower Releases Details Reports Of Activities In Thali Block Offshore Cameroon


Published: Monday July 4, 2022
By: Oilfield Africa Review

Tower Resources, the AIM-listed oil and gas company with a focus on Africa, has  provided an update on activity in respect of its Thali Production Sharing Contract (PSC), in the Rio Del Rey sedimentary basin offshore Cameroon.

Cameroon Financing

Tower Resources Cameroon SA (TRCSA), has executed a term sheet with BGFI Bank Group, the largest bank group in Central Africa, for a medium term loan of CAF 4.42 billion (equivalent to approximately US $7.1 million at the current exchange rate of 620 Central African Francs (CAF) to the US dollar) as partial financing of the NJOM-3 well on the Thali block in Cameroon.

The Loan should cover around 40% of the roughly US$18 million cost of the well, with a further amount in excess of 25% already having been paid for by TRCSA, and the balance of 35% of the cost of the well also to be funded by TRCSA. The term of the loan is five years and it will be secured by a modest restricted cash balance (or bank guarantee) and a partial parent company guarantee, as well as a pledge of revenues from Njonji production in due course.

Interest on the Loan is to be 8% per annum, with a moratorium on interest payments during the first year of the facility, and commissions and fees for BGFI for arrangement, participation and acting as agent for the facility are as customary.

The term sheet is not yet binding, and the Loan will be subject to, inter alia, the execution of definitive documents and the availability of the remaining funding required for the NJOM-3 well.

Cameroon Resource Update:

The NJOM-3 well will appraise the reservoirs already discovered and connected to the NJOM-1 well, and will also test additional reservoirs which are visible on the 3D seismic data which the company reprocessed in 2018 but which are not present at the edge of the Njonji structure where NJOM-1 was drilled.

The Company has prepared updated resource estimates for the reservoirs connected to the NJOM-1 discovery well. These estimates are a little higher than the estimates contained in the OIL Reserve Report (24.9 million barrels pMean recoverable compared with 17.9 million barrels per OIL).

https://bit.ly/39xAO1b

The main purpose of the updated resource estimate is not the slightly higher resource estimate per se, but the evaluation of additional potential reservoirs on a consistent basis  in the Northern section of the Njonji structure, which have been identified on the reprocessed seismic and which were not evaluated in the OIL report. These could amount to up to 20 million bbls of further resource, with a pMean estimate of 10.8 million bbls, albeit subject to chances of success in the range 23-32%.

The Company has also updated its estimate of the NPV10 of the base volumes in the 24.9 million barrel pMean recoverable case, to $305 million.


“We are delighted to announce this step forward in the financing of the NJOM-3 well, and also in our relationship with BGFI Bank Group. As we announced last month, the expected cost of the well has increased to approximately US$18 million, and so this facility and the US$4 million or so we have already invested, will still leave us with a balance – but a much smaller and more manageable balance – of the NJOM-3 well to finance. We are continuing to look at financing options at the asset level within TRCSA, including with Beluga Energy and its investors, though obviously for smaller amounts than discussed previously. We are also keeping an open mind on other financing alternatives, but whichever path we follow, as we explained in May, we expect the result to be considerably more favourable for shareholders than the farmout structure previously contemplated. We plan to conclude financing discussions in the third quarter of this year, as previously intimated, and then to press on with the well.

“As previously announced, long lead items for the well are already purchased, and the environmental and social impact assessment, site survey and site debris survey are already completed; and the initial exploration period of our Thali PSC has been extended expressly to accommodate this well.

“We are as excited as ever about the Thali PSC, as I plan to explain at the upcoming Proactive Investors conference in London this evening, 29 June 2022,” Jeremy Asher, Tower’s Chairman and CEO, commented.

Sponsored Partners

Discover our premium partners and explore their innovative solutions in the industry
Company News
Cakasa Completes Construction and Erection of Stockgap Mounded Bullet Tanks
Saturday November 1, 2025
Uganda
Uganda to Unlock 600 million Barrels in New Oil Finds
Friday October 31, 2025

Sponsored Partners

Discover our premium partners and explore their innovative solutions in the industry

Conferences & Exhibitions
NIES 2026:  Lokpobiri Tasks the Organizer for an Improved World-class Event
Tuesday October 28, 2025
Guinea Conakry
Guinea-Conakry Emerges as West Africa’s Next Oil & Gas Frontier
Tuesday October 28, 2025
Solar energy
TotalEnergies and Aljomaih to Build 400 MW Solar Power Project
Tuesday October 28, 2025
Seismics
Unlocking New Opportunities in the Permian Basin
Tuesday October 28, 2025
Downstream
NNPC Renews Commitment to Develop Downstream Infrastructure
Tuesday October 28, 2025
Mozambique
TotalEnergies is Going Back to the Mozambique LNG Project
Monday October 27, 2025
Exclusive
NCDMB Set to Train Over 10,000 Nigerians in High-Demand Oil Skills
Sunday October 26, 2025
Finance
Nigeria Exits Financial Action Task Force (FATF) Grey List
Sunday October 26, 2025
Conferences & Exhibitions
SAIPEC @ 10: Celebrating a Decade of Energy, Oil, and Gas Innovation in Sub-Saharan Africa
Sunday October 26, 2025
Company News
Baker Hughes Enlarges Coiled Tubing Scopes in Saudi Arabia
Sunday October 26, 2025
Uganda
UNOC Sends $38M Plus on Human Capacity Development
Wednesday October 22, 2025