Upstream

BP Matapal oilfield achieves early first gas offshore T&T


Published: Thursday September 23, 2021
By: Oilfield Africa Review

BP Trinidad and Tobago has confirmed its Matapal project has safely achieved first gas. The major milestone was achieved ahead of schedule and under budget despite the constraints brought about by the COVID-19 pandemic.   

Matapal is bpTT’s second subsea development. It’s comprised of three wells, which tie back into the existing Juniper platform, helping minimize development costs and the associated carbon footprint. It’s located approximately 80km off the south-east coast of Trinidad and approximately 8km east of Juniper, in a water depth of 163 metres.

Matapal will deliver gas into the Trinidad gas market from resources discovered by the Savannah exploration well, drilled in 2017. The initial production from this development is expected to be in the range of 250-350 million standard cubic feet per day (mmscfd), once all wells are fully ramped up. 

Sponsored Partners

Discover our premium partners and explore their innovative solutions in the industry

Gas & Power
Serica Energy Resumes Production Operations at Triton FPSO
Wednesday July 2, 2025
Gas & Power
LNG Canada Exports First Cargo to Asia
Wednesday July 2, 2025
Continental News
Press Release-NCDMB to Champion Nigerian First policy
Tuesday July 1, 2025